No. Project Name Funding Partners Component Description Design Area Implementation
New (ha) Rehabilitation
(ha)
Planned Period (From - To) Current Status Remarks
1 Rehabilitation of Tono Irrigation Scheme GoG Phase 1: Construct main canal of length, 37.6 km. Phase 2: Rehabilitate zones B (160 ha) and O (120 ha). Construct link road between 2 zones, install pumps, rehabilitate spillway, secondary & tertiary canals. Phase 3: Reconstruct tertiary canals, pipe lining, develop land and extend, land area by 320 ha. 2,490 2010-2013 Main canal of 37.6 km completed. -Link road, pump installation, spillway, secondary & tertiary canals rehabilitation completed. Reconstruction of tertiary canals, pipe lining and land development extension underway.
2 Torgorme Irrigation Scheme (Kpong Left Bank) MIDA/GoG Feasibility study, final design and construction supervision of rehabilitation/extension works 1,450 2011-2013 1,000 ha completed by Anchor farmer (Vegpro). 500 ha under cultivation. 450 ha about 85% complete.
3 Preparation of pre-investment framework and development of agricultural water management investment framework WB &GoG Identify, collect and compile data on all existing and potential irrigation and develop country support tool to determine the way forward for irrigation in Ghana 2011 - 2013 Pre-investment framework completed. Institutional reform programme on-going.
4 Dawhenya Integrated Rural Development Project (rehabilitation) Korean Govt &GoG Rehabilitate 200 ha rice field, - Replacement of pumps- Construct fish pond(1 ha), 2-storey training blk- Construct 12 unit classroom blk and 2 teachers accommodation 200 2011-2013 Project design completed Overseas Training on-going
5 Project for Improving Irrigation System for All-Year Round Tomato Production on the Akumadan Irrigation Scheme (rehabilitation) Korean Govt &GoG 60 ha additional area for vegetable prod.- Demonstration plots for drip and sprinkler irrigation 60 2011-2013 Irrigation equipment and other project inputs procured. Construction works ongoing, expected to be completed by Dec. 2013
6 Accra Plains Irrigation Project (APIP) Chinese Govt, World Bank/JICA&GoG - Construction of a 69km canal in the Accra Plains to irrigate 11,000ha 11,000 2012-2015 Prefeasibility study on 11,000ha completed by JICA for a gravity scheme. Feasibility & Detailed Design for 5,000 ha by STUDI. GIDA/MOFA has procured the service of Design and Build Contractor.
7 Bui Irrigation Project Chinese Govt/GoG Prefeasibility covering an area of 30000 ha. Feasibility covering an area of 5000 ha 5000 2011 - 2014 Draft feasibility report submitted
8 Nasia - Nabogo Valley Feasibility and Construction 10000 Feasibility World Bank under GCAP
9 Wieisi Valley Feasibility and Construction 63 Feasibility GIDA-NRGP
10 Gbedembilsi Feasibility and Construction 350 Feasibility GIDA-NRGP
11 Rehabilitation of 70 breached dams in the 3 Northern Regions Rehabilitation on-going facilities for livestock watering , domestic and irrigation
12 Study and rehabilitation of Vea Irrigation Scheme Feasibility Study and Rehabilitation 850 on-going Will be completed soon
13 Rehabilitation of 50 breached dams Assessment & Rehabilitation on-going Studies and BOQ ready for twelve (12) sites , assesessment of rest not ready.